Wednesday, December 19, 2007
Thursday, December 6, 2007
Crete
We have concrete!
We missed documenting a few steps along the way including: the rest of the pilings, the under slab plumbing, two inspections and the forming of the concrete- not to mention the 12 more loads of dirt we had to put on the ground to make our desired 11' elevation.
We poured the slab today at high noon and the boys finished slicking it about 6pm.
Next step: framing.
Tuesday, November 13, 2007
Pilings: Day 1
In order for them to get to the point where they can hammer, they first have to set the pilings a few feet into the ground by auguring holes to hold the posts in place. By the end of day 1 they have set 25 of the 37 pilings. They will need to wait to set the rest until they drive the ones in the back. The hammering should start sometime tomorrow.
Wednesday, November 7, 2007
The Pad
Sunday, November 4, 2007
Sunday Sandbox
Saturday, November 3, 2007
Friday, November 2, 2007
Dirty Jobs
15 loads of select fill were placed on the lot Friday morning, and we're off and running. We are scheduled to get the remaining 30 or so loads first thing Monday. We'll spend next week building up the pad, grading the lot and preparing for pilings while we wait for our permits. Everybody is really excited to get started and were going to do our best to get the ball rolling quickly- it's good to be back in construction mode!